Work is not considered complete when the coating has been applied, but when the full documentation package has been signed off. Records must be compiled as work progresses: reconstructing site logs and concealed-work inspection certificates retrospectively is virtually impossible.

Core documentation package

  • Calculation of required coating thickness by structural group
  • Certificates of conformity and test reports for materials used
  • Batch certificates and delivery documents
  • Fire-protection work log
  • Inspection certificates for concealed work (surface preparation and priming)
  • Dry-film thickness inspection reports referenced to gridlines and elevations
  • Certificate of completion for fire-protection work in the prescribed form

Why do inspectors raise comments?

Most often, this is due to discrepancies between the calculations, the material actually applied and coating-thickness measurements. Another common issue is the failure to link measurements to specific structural members, making it impossible to reconcile the inspection report with the design.